Africa’s Green Hydrogen Race: Big Promises, Slow Reality

Wind turbines and solar panels in a desert with mountains behind.

Africa has announced 78 green hydrogen projects worth $194 billion, with about 38 gigawatts of planned electrolyser capacity. It has two green hydrogen projects actually running, with a combined capacity of 17 megawatts — both of them in Namibia. That gap between the announcement and the reality is the story of African green hydrogen: the continent has the sun, the wind, the land and the coastline to become a clean-fuel exporter, but almost none of it has been built yet.

Green hydrogen is hydrogen made by splitting water with renewable electricity. It can replace fossil fuels in fertiliser, steel, shipping and power generation, and Europe — which plans to import 10 million tonnes of hydrogen a year by 2030 — is the main target market. This guide explains the projects, the money, why so little is moving, and what would have to change.

The projects: five countries, one pipeline

Five countries hold nearly all of Africa’s hydrogen ambition. Egypt, Morocco and South Africa account for about 80% of the planned capital spending; Namibia and Mauritania hold the biggest single projects.

Country Flagship projects Scale
Namibia Hyphen Hydrogen Energy $10 billion; about 350,000 tonnes a year at full scale (Phase 1: 175,000 tonnes)
Egypt SCZone project; Scatec; AMEA Power; Masdar $40 billion national investment plan; Egypt alone holds $88.5 billion of planned investment
Morocco ORNX Laâyoune ammonia project; others approved $32.5 billion of projects approved
Mauritania AMAN (CWP Global); Megaton Moon (GreenGo); Project Nour (Chariot); Nouakchott (Conjuncta–Infinity) 12.5 million tonnes a year targeted by 2035
South Africa Sasolburg (Sasol with Envision Energy) Design-stage green hydrogen for fuels and chemicals

The Namibian project is the bellwether. Hyphen’s $10 billion development — roughly two-thirds of Namibia’s annual GDP — aims to produce about 350,000 tonnes of green hydrogen a year at full scale, turned into ammonia for export, with the government as a partner in the project. A final investment decision is expected at the end of 2027, with first production in 2028. If Hyphen reaches it, it becomes the first African green hydrogen project of real scale. If it does not, the continent’s pipeline stays on paper.

Mauritania’s ambition is the largest on paper: a pipeline of gigawatt-scale projects targeting 12.5 million tonnes a year by 2035, including the 1.7-million-tonne AMAN project and the 8-million-tonne Nouakchott project. Egypt has the most projects of any African country and a $40 billion investment plan. Morocco has approved $32.5 billion of projects and is building towards exporting ammonia from Laâyoune, where the U.S. Trade and Development Agency is funding design work on a 560,000-tonne-a-year ammonia plant. Tunisia plans to send 300,000 tonnes a year to Europe by 2030 through the proposed SoutH2 pipeline.

The gap, in numbers

The Energy Industries Council’s Africa Hydrogen Report, published in January 2026, puts the scale of the gap in hard figures. Afrikeye has calculated the ratios from its data:

That is not a failure of ambition. It is the normal shape of a new industry that needs billions in upfront spending before it earns a cent — and it is the reason the next two years matter more than the last five.

Why projects stall

Three problems recur in every stalled African hydrogen project, and the EIC report names all three: no firm offtake agreements, insufficient pipeline and port infrastructure, and a local supply chain that barely exists.

No buyers signed. A hydrogen plant costs billions to build and only makes sense if someone has already agreed to buy its output for years. European buyers want African hydrogen, but few have signed the long-term contracts that would let a project raise finance. Without offtake, there is no final investment decision; without a decision, there is no construction.

No way to move it. Hydrogen is hard to transport. It must be turned into ammonia, shipped, and turned back — or sent through pipelines that do not exist yet. The SoutH2 pipeline from North Africa to Europe is still a proposal. Ports, storage and dedicated export terminals all need building, and each adds cost and delay.

High cost, thin margins. Producing green hydrogen in Africa should eventually be cheap — the sun and wind are free. But forecasts vary widely: the European Investment Bank puts production below €2 a kilo by 2030, while a 2025 academic study put realistic costs at €4.2–4.9 a kilo without de-risking. The first plants pay full price for electrolysers, renewables, water desalination and infrastructure, in countries where capital is expensive. Until costs fall and buyers commit, most projects stay at feasibility stage.

What is actually moving

Not everything is stalled. Namibia leads the continent on execution: it hosts three of the five projects currently under construction and one already operating, and Hyphen is the furthest advanced of the mega-projects. Egypt has the largest number of projects at feasibility stage. South Africa and Morocco host the continent’s only two demonstration projects, which indicates higher technical readiness than elsewhere.

Money is also starting to move in small amounts. In September 2026 the African Development Bank selected four green hydrogen projects in Egypt, Morocco, Namibia and South Africa for $20 million in reimbursable grants — funding that must be repaid — subject to Board approval. That is small against the billions needed, but a signal that development finance is backing specific projects rather than general ambition. GIZ’s African Green Hydrogen Report expects the number of projects coming online to rise from two in 2025 to 13 by 2030, with Egypt, Mauritania and South Africa leading the next wave — if the financing and offtake problems are solved.

The lesson from Africa’s other energy bets applies here too. Senegal’s oil and gas projects took years from discovery to first production, and only moved when buyers, pipelines and financing were all in place at once. Hydrogen will follow the same rule: announcements are cheap, and delivery needs everything at the same time.

What happens next

Watch four things. First, whether Hyphen in Namibia reaches a final investment decision — the first African FID at scale would unlock finance for the projects behind it. Second, whether European buyers sign long-term offtake deals, particularly with Egypt and Morocco, whose hydrogen is aimed at the European market. Third, whether the SoutH2 pipeline and the ammonia export terminals move from proposals to construction. And fourth, whether the 13 projects GIZ expects online by 2030 actually arrive — the gap between that forecast and today’s two operating projects is the honest measure of whether Africa’s hydrogen race is real.

The stakes are large. One analysis by the Africa Green Hydrogen Alliance estimates green hydrogen could add $126 billion to the GDP of Egypt, Kenya, Mauritania, Morocco, Namibia and South Africa by 2050 — about 12% of their current GDP. But that figure is a forecast, not a promise. As with the climate finance debated at COP31 in Antalya, the question is not whether the money exists on paper. It is whether it arrives. We will keep tracking the race in our Business coverage.

Frequently asked questions

What is green hydrogen?
Hydrogen produced by splitting water using renewable electricity, such as solar or wind power. Unlike hydrogen made from natural gas, it produces no carbon emissions in the process.

Which African country leads in green hydrogen?
Namibia is furthest ahead on execution, with projects under construction and one operating, led by the $10 billion Hyphen project. Egypt has the most projects and the largest planned investment.

Why is so little actually built?
Projects need firm buyers, pipelines and ports, and billions in upfront finance. Only one of 31 African projects targeting 2030 had reached a final investment decision, according to the IEA’s 2026 review.

Who would buy African green hydrogen?
Mainly Europe, which plans to import 10 million tonnes a year by 2030, and Asian markets such as Japan and South Korea, which would buy ammonia made from African hydrogen.